Council News ·

Counties seek designs for two sets of traffic lights in Russell

A green traffic signal against blue sky in Gatineau, Que.
Traffic signal in Gatineau, Que. File photo: Paul MARSAN / Unsplash.

The United Counties of Prescott and Russell and Russell Township are looking for an engineering firm to design traffic lights at two intersections in the village of Russell: Concession Street at Castor Street and Concession Street at Craig Street.

Both intersections now have stop signs. The counties’ request for proposals also calls for designs for related road improvements and for the firm to administer the construction contract. Proposals are due Nov. 26 at 3 p.m. The posting does not give a construction start date.

Charles Armstrong said during the election that the lights were “scheduled for installation in the Village of Russell in the next two years.”

The township’s Transportation Master Plan recommends signals at both intersections to improve traffic flow and provide safer crossings for pedestrians and cyclists. The plan projects long delays at both intersections during the afternoon rush by 2044 if no improvements are made.

The township plan puts the combined capital cost at an estimated $2.8 million. The counties’ 2025 asset management plan lists separate estimates of $605,000 for Castor and $765,000 for Craig, or $1.37 million combined. Neither figure is a construction contract price, and the bid notice does not reconcile the two estimates.

In Embrun, the township’s transportation master plan recommends traffic lights on Notre-Dame Street at St-Joseph Road and at St-Thomas Road, both beyond 2044. The plan identifies possible cost sharing with the counties, but no funding agreement has been confirmed. The two Russell intersections are already out for design bids. The Embrun lights are still a recommendation in the plan.