Russell recreation complex occupancy delayed again

Russell Township recreation complex under construction in September 2026
Photo supplied by Russell Township.

Russell Township now expects to take occupancy of the arenas and community hall at its new recreation complex on Jan. 7, 2027, nearly four weeks later than the Dec. 11 date reported last month.

The aquatic facility’s anticipated occupancy date has also moved from Feb. 14 to Feb. 28 according to a staff report prepared for council’s Nov. 16 meeting.

Neither date is a public opening date. Staff say testing, equipment setup, training and other preparations must be completed before residents can use the facilities.

Staff attribute the revised arena and community hall forecast to a detailed review of the commissioning schedule and dates remain subject to outstanding work, correction of deficiencies and regulatory approvals. The township continues to plan a phased opening with the arenas and community hall operating before the pool. The latest revisions follow concerns councillors like Jamie Laurin raised at the Oct. 13 meeting.

“I get it. I’m not happy, but I get it,” Laurin said at that meeting.

Mayor Mike Tarnowski also spoke about the earlier delay at the Oct. 13 meeting saying “I’m not happy about the delay” while noting the scale of the project.

Parks and recreation director Céline Guitard told councillors in October that upcoming discussions about commissioning and training would help clarify the schedule.

“So when we come back in next council in November, I think we’ll again have a more precise date.”

The new report is listed for information at Monday’s council meeting, which begins at 6 p.m. at Gaston R. Patenaude Hall, 717 Notre-Dame St. in Embrun.